Allston LabWorks is a 585,000 SF mixed-use development located in Allston, MA.  Upon completion, the project will contain class A laboratory space, ground floor retail, residential units, and community spaces open to the public.  

FOLLOW THE PROJECT UPDATES

Construction Schedule

Two Week Lookahead

*Work is scheduled for this Saturday, 6.22

250 Western Ave

Week of 6/24

- Exterior facade work will continue.

- Deliveries expected every day at Gates B and C.

- Delivery trucks will access the project site via Western Ave and or Everett St. and return to the expressway via Western Ave. No truck access on N. Harvard St.

Next Week 7/1

-All tasks will be performed above.

- Exterior facade work will continue.

- Deliveries expected every day at Gates B and C.

- Delivery trucks will access the project site via Western Ave and or Everett St. and return to the expressway via Western Ave. No truck access on N. Harvard St.

280 Western Ave

Week of 6/24

-Exterior metal panels being installed on the east side of the building.

-Deliveries are expected every day at Gates A and B.

-Delivery trucks will access the project site via Western Ave and or Everett St. and return to the expressway via Western Ave. No truck access on N. Harvard St.

- Sitework ongoing at all areas around the site.

- Minor impacts in 300 Western Ave parking lot ongoing.

Next Week 7/1

All tasks will be performed above.

305 Western Ave

Week of 6/24

- Misc delivery trucks (18 wheelers) will access the project site via Western Ave and or Everett St. and return to the expressway via Western Ave. There will be a state police detail for deliveries on Everett St. No truck access on N. Harvard St.

Next Week 7/1

- All tasks will be performed above.

Upcoming Impacts

-Saturday, 6.22: A crane will be brought onto site to hoist duct work onto the roof of 250 Western Ave. The crane will sit on the west side of the 250 Western Ave. building within the site fence.

- Ongoing - Support of excavation wall is being built on the south side of the 250 and 280 Western Ave sites. Excavators and man power will be on the south side of the site for several weeks. All work will be performed within the site fence.

- Upcoming - A wood fence will be built on the south side of the 250 and 280 Western Ave sites. Site fence will be taken down as wood fence is installed.

- Upcoming - Fire alarms will be tested at 280 Western Ave.

-Upcoming- From July 12 to July 14, the tower crane at 305 Western Ave will be dismantled. There will be traffic impacts.

.

Connect With Us

We'd love to hear from you!

If there are any issues or concerns with the construction project or the project site, please let us know via the form or number below.

646-679-3534
Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.